2 PIECE ALUMINUM STANDOFF WITH FLASHING & L-FOOT:
If necessary cut an opening in the roong material over a rafter to accommodate the
ashing riser.
Install the standoff, ensuring that both lag bolts are screwed into the rafter.
Insert the flashing under the shingle above and over the shaft of the standoff.
(No-Calk™ collar does not require sealing of the ashing and standoff shaft)
Add L-Foot to top with bolt that secures the EPDM washer to the top of the standoff.
See Standoffs & Flashings Installation Manual 907.2 for Additional Details.
DRILL PILOT HOLES: Center the roof
attachment over the rafter and drill a
pilot hole(s) for the lag bolt(s).
NOTE: Determine lag bolt size and embedment
depth.
Quick Tip: Pre-drill the pilot hole through the at
ashing lag bolt location for easier installation.
FLAT FLASHING INSTALLATION: Insert
the Flat Flashing so the top part is
under the next row of shingles and the
hole lines up with the pilot hole.
INSTALL LAG BOLTS & L-FOOT:
Insert the lag bolt through the L-Foot
in the order shown in the illustration.
Verify proper orientation before
tightening lag bolts.
See Unirac Flat Flashing Manual for
Additional Details.
ROOF ATTACHMENT & L-FEET
E
ROOF PREPARATION: Layout and
install ashing at rafter locations
determined per Design and
Engineering Guide.
TOP MOUNT TILE HOOK & L-FOOT:
Remove or slide up the roof tile, position the roof hook above the roof rafter
Place Tile Hook in the middle of the underlying interlocking tile’s valley. Drill 3/16
inch pilot holes through the underlayment into the center of the rafters. Securely
fasten each tile hook to the rafters with two 5/16” x 3½” lag screws. Slide down or
re-insert the tile.
Attach L Foot to tile roof hook.
See Tile Hook Universal Mount Installation Manual for Additional Information.