User's Manual
Chapter 3 Installation
3.14.3 Terminating a 7/8” EIA Flange Output
The fol
lowing steps should be performed to terminate a 7/8” EIA flange output:
1. Insert an inner connector into the 7/8” EIA flange – see Figure 3-54
.
2. Place a rubber ring in the 7/8” EIA flange groove – see Figure 3-54
.
3. Connect the transmission line to the 7/8” EIA flange according to site drawings.
4. Secure the transmission line in place by installing a 1/4-20x1” hex head bolt with
1/4” flat washer and 1/4” lock washer in each of the threaded holes (3 total) – see
Figure 3-53
. A torque rating of 45 In. Lbs. should be used to tighten the bolt.
Figure 3-54 7/8” EIA Flange Connection (before and after)
Picture TBD
1) Inner Connector
2) Rubber Ring
3) 1/4-20x1” Hex Head Bolt with 1/4” Flat Washer and 1/4” Lock Washer
SX03-30000-01-M01
3-63