This section describes the installation procedures for the DRU-200, which is to be installed
in a restricted access location.
3.2 Components/Sub-Assemblies Installed at the Factory
The following components/sub-assemblies are installed in a Combined DRU cabinet prior to
shipping.
Table 3-1 Combined DRU Components/Sub-Assemblies Installed at the Factory
Name Part Number Quantity
PDU SX03-10300-01 1
Low Noise Amplifier (LNA) SX03-50100-01 1
Dual Band Pass Filter (DBPF) SX03-50200-01 1
BMS Mounting Shelf w/Controller SX03-50300-01 1
BMS 12 VDC Battery SX03-50330-01 1
Air-to-Air Heat Exchanger/Heater SX03-50400-01 1
Break Out Board SX03-92020-01 1
7/8” Short U-link/Coupler SX03-10402-01 2
Fan (Blower) Box SX03-50500-01 1
7/8” Combined Output
Coupler/RF Detector
SX03-51430-01 1
HPA PSU Mounting Shelf SX03-51710-01 1
NOTE: A number of other components, which were installed in the cabinet prior to shipping,
are not listed in Table 3-1
. They include:
• Surge protectors
• Connectors, adapters and flanges
• Mounting brackets and panels
• Ground, AC, DC and communications wires
• RF cables
SX03-10000-01-M01 3-1