Installation manual
UNIPOWER
Installation manual PQ Secure
31
5 INSTALLING PERMANENT RECORDER UP-2210-R
The installation process involves fitting the recorder in an existing 19-inch cabinet at the selected
installation site. The recorder is also connected to existing instrument transformers and the chosen
communication equipment. Working with transformers must only be made by qualified personnel to
prevent injury during installation. We recommend making the connections to the measure core and
only in exceptional cases directly to the relay cores.
5.1 Location and fitting
UP-2210-R is designed to be installed in a 19-inch cabinet. You should think carefully about the
environment so that it is clean and dry and have a normal ambient temperature. The communication
with the unit can also influence where the unit is installed.
Figure 21
The figure above shows a UP-2210-R. The UP-2210-R can be used with all standard 3-phase
connection options, and can measure both line-to-neutral and line-to-line voltages.
Note: If the units are used with external/internal modem, keep in mind that phone lines are
easily affected by lightning. Modems usually don’t have lightning protection. Unipower
recommends that external lightning protection is installed between the phone line and
modem in exposed locations, in order to protect the unit from damages caused by
lightning.