Installaon Instrucons
Unroll RAM Vent™ along the perimeter of the foongs on top of the soil.
Lay a cross piece of RAM Vent™ through the center parallel to the longest wall every 15 to 20 feet. Then, overlay the
suboor with a vapor barrier extending up the wall.
Cut a 3” (8cm) hole in the vapor barrier near the most appropriate corner. Next, glue a 4” (10cm) anged riser pipe with a
detachable cap to the vapor barrier and sing on top of RAM Vent™ (The pipe stub should be long enough to extend above
the top of where the slab is poured). Then, pour the slab. Finally, extend the vent pipe through the roof.
Addional Instrucon— Make sure to seal any cracks/ seams etc. on top of the concrete with a sealant, such as silicone.