26  INSTALLATION — Shower base with Schluter
®
-KERDI-DRAIN
Remove the clamping ring from the installed 
drain and save the bolts. Align the bolt 
pattern of the clamping ring with the adaptor 
ring and punch the matching inserts through 
the adaptor ring.
1
Apply a 1/4" - 3/8" (6 mm - 10 mm) bead 
of KERDI-FIX to the installed drain flange. 
Place the adaptor ring on the installed 
drain, re-insert the bolts, and tighten evenly. 
Make bolts finger-tight plus 1/4 turn;  
over tightening may warp the ring and result 
in leaks.
2
Slide the adaptor flange into the adaptor ring 
and ensure full support under the adaptor 
flange with mortar. The mortar bed is then 
placed according to the instructions on 
page 25.
3
Clamping Ring Drain Installed:  If a clamping ring drain is installed, replace with KERDI-DRAIN or convert using the KERDI-DRAIN adaptor kit.
If necessary, cut the KERDI-BOARD-SC to length using a utility knife and KERDI-SHOWER-SC/-SR using a handsaw.
1
1
Apply Schluter SET
TM
, ALL-SET
TM
, FAST-SET
TM
, 
or unmodified thin-set mortar to the floor 
and to the edge of the shower base and 
walls using a 1/4" x 3/8" (6 mm x 10 mm) 
square- or U-notched trowel.
Apply Schluter SET
TM
, ALL-SET
TM
, FAST-SET
TM
, 
or unmodified thin-set mortar to the floor 
and walls using a 1/4" x 3/8" (6 mm x 10 
mm) square- or U-notched trowel.
2
2 3
Press the curb or ramp firmly into place. 
Check the underside of the curb or ramp 
to ensure that full coverage and support  
is achieved.
Press the bench firmly into place and check 
the underside and backsides to ensure that 
full coverage and support are achieved. 
Verify that the slope on the surface of the 
bench is directed toward the shower base.
Schluter
®
-KERDI-BOARD-SC curb and Schluter
®
-KERDI-SHOWER-SC/-SR curb  
or ramp
Schluter
®
-KERDI-BOARD-SB bench
Note: Schluter
®
-KERDI-BOARD can be used to 
build custom curbs.
Install KERDI-BAND and KERDI-KERECK 
and KERDI-KERS-B (for triangular bench) 
to cover all seams and corners, ensuring a 
minimum 2" (50 mm) overlap, and work the 
membrane into the mortar to achieve full 
coverage and remove air pockets.
Note: Schluter
®
-Systems recommends a leak test be performed on the connection between the drain 
and the waste line prior to continuing with the remainder of the installation whenever possible.