INSTALLATION GUIDE US 2018
P3 JOIST Storage and Handling Guidelines 1. Store, stack, and handle P3 Joists in a vertical and level position only. 2. Do not store P3 Joists in direct contact with the ground; do not store P3 Joist flatwise. 3. Protect P3 Joists from weather, and use stickers to separate bundles. 4. To protect P3 Joists further from dirt and weather, do not open bundles until time of installation. 5.
Allowable Floor Spans Maximum Allowable Spans NOTES 1. Allowable clear span is applicable to simple-span or multiple-span residential floor construction with a design dead load of 10 psf and a live load of 40 psf. The live load deflection is limited to L/480. (L = span length in inches). Spans are based on duration factor (LDF) of 1.0. 2.
Web Stiffener Requirements Minimum Nailing Requirements for Web Stiffeners Stiffener Size and Nailing Requirement 3-1/2” Wide Flange 10d (3”) nails 4 4 4 6 6 8 8 1-1/2” x 2-5/16” (width) 2-1/2” Wide Flange 8d (2-1/2”) nails 4 4 4 4 1” x 2-5/16” (width) Joist Dept 9-1/2” 11-7/8” 14” 16” 18” 20” 22” 24” Minimum Stiffener 1.
Installing P3 Joist 1. Before laying out floor system components, verify that P3 Joist 10. Restrain ends of floor joists to prevent rollover. Use Certified Rim Board, rim joists, or P3 Joist blocking panels. flange widths match hanger widths. If not, contact your supplier. 2. Except for cutting to length, never cut, drill, or notch P3 Joist flanges. 3. Install P3 Joists so that top and bottom flanges are within 1/2” of true vertical alignment. 11.
FIGURE 2 (CONTINUED) Typical P3 Floor Joist Framing and Construction Details All nails shown in the details below are assumed to be common nails unless otherwise noted. 10d box nails (0.128 x 3”) may be substituted for 8d common (0.131 x 2-1/2”) as shown in details. Individual components are not shown to scale for clarity.
FIGURE 2 (CONTINUED) Typical P3 Floor Joist Framing and Construction Details All nails shown in the details below are assumed to be common nails unless otherwise noted. 10d box nails (0.128 x 3”) may be substituted for 8d common (0.131 x 2-1/2”) as shown in details. Individual components are not shown to scale for clarity. Transfer load from above to bearing below. Install squash blocks per 2d. Match bearing area of blocks below to post above.
FIGURE 2 (CONTINUED) Typical P3 Floor Joist Framing and Construction Details All nails shown in the details below are assumed to be common nails unless otherwise noted. 10d box nails (0.128 x 3”) may be substituted for 8d common (0.131 x 2-1/2”) as shown in details. Individual components are not shown to scale for clarity. Glulam or multiple structural composite lumber (SCL) beams For nailing schedules for multiple SCL beams, see the manufacturer’s recommendations.
FIGURE 2 (CONTINUED) Typical P3 Floor Joist Framing and Construction Details All nails shown in the details below are assumed to be common nails unless otherwise noted. 10d box nails (0.128 x 3”) may be substituted for 8d common (0.131 x 2-1/2”) as shown in details. Individual components are not shown to scale for clarity.
Cantilever Details for Interior Balconies (No Wall Load) FIGURE 3 Cantilever extension supporting uniform floor loads only Attach P3 Joists to plate at all supports per Detail 2b. CAUTION Cantilevers formed this way must be carefully detailed to prevent moisture intrusion into the structure and potential decay of untreated P3 Joist extensions. 3-1/2” min.
Cantilever Detail for Vertical Building Offset (Concentrated Wall Load) FIGURE 5A Method 1 Sheathing Reinforcement One Side Method 2 Sheathing Reinforcement Two Sides APA Rim Board or wood structural panel closure (23/32” minimum thickness) Attach per Detail 2b P3 Joist blocking panel or APA Rim Board blocking Attach per Detail 2g Attach P3 Joist to plate. 6” Str en 2-1/2” nails ma 2’–0 xim ” um 3-1/2” min.
Cantilever Details for Vertical Building Offset (Concentrated Wall Load) FIGURE 5B 13’–0” maximum Roof trusses Girder truss Hip trusses Roof truss span Roof truss span 2’–0” maximum cantilever See Table below for P3 Joist reinforcement requirements at cantilever. 2’–0” maximum cantilever For hip roofs with the hip trusses running parallel to the cantilevered floor joists, the P3 Joist reinforcement requirements for a span of 26 ft. shall be permitted to be used.
Web Hole Rules and Specifications One of the benefits of using P3 Joists in residential floor construction 6.
Web Hole Rules and Specifications (continued) TABLE 4 Location Of Circular Holes In P3 Joist Webs Simple or Multiple Span for Dead Loads up to 10 psf and Live Loads up to 40 psf1,2,3,4 Joist Depth 9-1/2” 11-7/8” 14” 16” 18” 20” 22” 24” Joist PJI 40 PJI 60 PJI 40 PJI 60 PJI 80 PJI 90 PJI 40 PJI 60 PJI 80 PJI 90 PJI 40 PJI 60 PJI 80 PJI 90 PJI 80 PJI 90 PJI 80 PJI 90 PJI 80 PJI 90 PJI 80 PJI 90 2 SAF(5) 14’-6” 0’-7” 15’-3” 1’-8” 16’-7” 0’-7” 18’-2” 0’-8” 19’-10” 1’-11” 20’-5” 2’-1” 18’-3” 0’-7” 19’-9” 0
P.
Sales Contact: Jeff Kilgour EACOM Timber Corporation 1100 René Lévesque Blvd. West, Suite 2110 Montreal, Québec H3B 4N4 www.eacom.ca P3sales@eacom.ca ©2018 EACOM Timber Corporation – January 2018 Plant: EACOM Timber Corporation 1195 Peoples Road Sault Ste.