The following virtual channels are defined:
Channel 0: control channel
Channel 1 5: AT commands / data connection
Channel 6: GNSS tunneling
Channel 7: SAP (SIM Access Profile)
For more details, see the Mux implementation Application Note [14].
If the module switch-off AT command +CPWROFF is issued over a multiplexer channel, the
completion of the module power-off sequence could require up to 2.5 s, after the module OK reply.
Therefore, if the application processor (AP) controls the VCC supply of the module, the AP should
disable the multiplexer protocol and then issue the AT+CPWROFF command over the used AT
interface, or otherwise the AP should issue the AT+CPWROFF command over a multiplexer
channel and wait 2.5 s after OK reception before removing the module VCC supply.