3. Using a lifting device, raise the Overhead Beam assembly and
connect to uprights at each end, using the bolts, nuts and washers,
as shown in (Fig. 9).
4. Use a tape measure to measure the diagonal distance between the
opposite corners of the base plates on the columns. Equal values
will ensure the lifting arms will be in square.
5. Secure OFFSIDE column to the floor following the same
procedures as outlined in STEP 4.
Fig. 9
STEP 6: (Installing POWER UNIT)
1. Attach the power unit to the mount bracket on the side of the Main
Column using bolts, nuts and washers supplied (Fig. 10).
2. Remove the vent plug from the power unit and fill the reservoir with
hydraulic oil. Make sure the funnel used to fill the power unit is
clean.
Suggestion: Use AW 32, or 46 Non-Detergent Non-Foaming Anti-Wear
Hydraulic Oil SAE-10 (Texaco HD46 or equal). The unit will
holds approximately ten quarts of fluid.
Fig. 10
STEP 7: (Installing / Routing EQUALIZER CABLES)
1. Raise and lock each carriage on the first safety latch engagement, approximately 30” high.
2. Make sure that the safety locks on each column are fully engaged before attempting to route equalizer
cables.
3. Be sure each carriage is at the same height by measuring from the top of the base to the bottom of the
carriage. This difference should be within 1/4”.
4. Route the first cable. (See Figs 11-14) Screw the nut on the cable stud so that half thread pass through
the nut. Pull the other end of the cable and screw the nut on it also. Then tighten both nuts.
Fig. 11 Fig. 12 Fig. 13
(See Fig. 14 next page, for Cable Routing Diagram)