Product Manual

13
TP12KFX
Feb 2017-B
STEP 10: (Electrical Connection to POWER UNIT)
1. Have a certified electrician make the electrical connection to the power unit. Use separate circuit for
each power unit, as shown below in (Fig. 19).
Fig. 19
IMPORTANT! The wiring must comply with local code. Protect each circuit with time delay fuse or
circuit breaker. For 208V-230V single phase, use 20 amp fuse. WARNING!! Never operate the motor in
line voltage less than 208VAC as motor damage may occur.
STEP 11: (Checking Operation) See next page for detailed Operation Instructions:
1. Do not place any vehicle on the lift at this time. Cycle
the lift up and down several times to ensure carriage
latches click together and all air is removed from the
hydraulic system.
2. To lower the lift, both carriage’s safety latch releases
must be manually pulled down to be released to lower
lift (Fig.20). The latches will automatically reset once
the lift ascends approximately 17” from base.
3. If latches click out of sync, tighten the equalization
cable on the one that clicks first.
Fig. 20
THE LIFT IS NOW READY FOR USE.