16. Begin cable routing installation to Column Top Caps by first ensuring the pre-installed steel 
Cables are properly routed around each Cable Sheave and are not in a bind. Note: if 
Cable(s) comes off the Cable Sheave, it will be required to remove the Cable Sheave 
assembly to reinstall the Cable, due to welded cable guide brackets. 
17. Pull the slack for each Cable from the corner ends of the Mainside Runway and route the 
appropriate Cable(s) to each Column Top Caps, while ensuring that the Plastic Cable Pulley 
(#95) is between the Cable and the Lock Ladder as shown in Fig.7. This will allow the 
secondary Slack Cable Lock to function properly.  See Fig.7 below for Cable routing 
installation.  
Fig. 7 
Plastic Cable 
Pulley 
Nylon Lock Nut 
& Washer 