14. Stand up and arrange the two end structures (Columns & Crossbeams) so that the outside of 
the Crossbeam rail to the outside of the other Crossbeam rail measures 188.5”. Compare the 
measurements from the left and the right until they are diagonally within 1/2”. Note: The ½” 
variance will help in mounting the runways later. 
15. Lift and position each Runway into place and secure to top of Crossbeams with the provided 
Hex Bolts (#24), Lock Washer (#25), Flat Washer (#26), as shown in Fig. 6. The lift will square 
itself as you further assemble it. 
Note: Ensure to install the ‘offside’ Sub Runway opposite from the Main side Runway and 
Power unit Column as shown in Fig.6. 
Fig. 6 