Installation Guide

T0073500 Rel-0004
©2020 Caretaker In-Floor Systems
7 of 166-Port
Cleaning Head Risers
Risers or stub-ups are glued into 2" (5.1 cm) Tee's, 90-degree elbows, to stub-ups through the
pool shell.
Match the riser width to collar width.
2" collars require 2" class 200 pipe (no reaming required) or 2" schedule 40 pipe (reaming
required)
2.5" collars require 2.5" (6.35 cm) Schedule 40 Pipe (no reaming required)
Position stub-up perpendicular (90°) to the slope
of the finished pool floor and secured to avoid
movement durring gunite process. (see Figure 3)
Top of stub-ups must be 6" (15.2 cm) above
finished elevation.
During gunite application, leave a
1" (2.5 cm) deep x 1" (2.5 cm) wide well around
each stub-up.
Note: If 2" schedule 40 stub-ups are used, pipe reamer (part #
4-17-2) is required to allow the 2" collar to fit into the pipe.
Hint: Save plumbing time by using 2.5" (Part # 5-9-150) or 2"
(Part #WK000001) Prefabricated stub ups. They glue directly
into 2" schedule 40 fittings, don't require reaming and are
ready for pressure testing.
Auxiliary Equipment
Pump: Choose an appropriate pump size and style to meet the GPM flow rate minimums
specified on your certified pool plan. For variable speed pumps, see page 12.
Heaters: To compensate for heater system pressure drops, plumb heaters in a bypass line
before the water valve, even if the heater has an internal bypass. Perform a temperature rise
test to determine where to set the bypass valve (see Figure 7). Ensure proper water flow can
be reached.
Chlorinators: In-floor systems can be used with erosion feeders, ozone generators, and
in-line salt-chlorine generators. Consult manufacturers' instructions for proper installation
to protect the water valve and other pool equipment from high concentrations of chlorine or
chlorine gas.
Automatic Pool Cleaners: When using an automatic pool cleaner with the in-floor system,
plumb the dedicated cleaner line (booster pump if applicable) before the valve (see Figure 4)
.
Water Features, Falls and Returns: Plumb so the 6-port valve receives the GPM's
mentioned in the certified design during the cleaning sessions.
Filters: Use of a filter is required to maintain warranty. Size the filter to exceed the flow
requirements of the certified design. Consult manufacturers' installation instructions.
To Pool
To Cleaner
6-Port
Valve
Heater
Filter
Pump
From
Pool
Figure 4. Example of a Plumbing Setup
90
45° or Sweep
2" Feed Line
2-1/2"
Prefab Riser
(Stub-up)
90
6" min.
1in.
1 in. well in gunite
around each
stub-up
Figure 3. Cleaning Head Risers
1
0
2
0
3
0
4
0
5
0
6
0
psi
1
0
0
2
0
0
3
0
0
4
0
0
1
2
3
4
kPa
bar
Valve
Pressure
Gauge