SONET OC-3 Link Performance Test
28 GHz SONET OC-3 IFU Installation - R1.0 4-9
5 Set up both SONET test sets for DS-1 testing.
6 Test sets will sync up with each other and run head to head. Record the
results in Table A-5.
7 A frame/bit error can be injected and received to further demonstrate a
good path during all tests.
8 If all tests run error free and the cabling and termination are correct, all
tests pass.
Figure 4-3. SONET Link Test Setup
FAR-END IFU
NEAR-END IFU
PROTECTED
PAYLOAD
PAYLOAD
SONET TEST SET
OUTSIDE BUILDING
INSIDE BUILDING
OUTSIDE BUILDING
INSIDE BUILDING
BLUE
RECEIVE
RX
TX
ORANGE
TRANSMIT
IFU A IFU B
PATCH PANEL
SONET TEST SET
BLUE
RECEIVE
RX
TX
ORANGE
TRANSMIT
IFU A IFU B
PATCH PANEL