Installation Manual

Table Of Contents
Commissioning Procedures
4-6 © 1999 Triton Network Systems, Inc. All Rights Reserved.
Commissioning the IFU
To commission the far-end IFU:
1 Ensure the near-end IFU transmitter is set to ON.
2 Loosen the four vertical screws on the holding bracket.
3 While viewing the multimeter, sweep the IFU vertically by pointing the
IFU all the way up and then down. The measured voltage of the
multimeter displays a succession of peak signals as the IFU moves.
Specifically, the signal displays a small peak, a relatively higher peak,
and then redisplays the small peak. Note the approximate position of
the IFU when the higher peak occurs and the corresponding voltage
value. The peak voltage should be approximately 3 Vdc.
4 Move the IFU to the higher peak position as indicated by the multimeter
display.
5 Tighten the four vertical screws on the IFU mounting bracket.
6 Loosen the horizontal alignment nut on the IFU mounting bracket.
WARNING: Beware! Radio transmitter is ON when the
red light indicator on back side of Invisible Fiber unit is
illuminated. Observe all radio frequency energy exposure
and service interruption cautions.
MISE EN GARDE : Attention ! Le poste émetteur est EN
MARCHE lorsque le témoin rouge sur le dos de lunité
Invisible Fiber
MD
est allumé. Respecter toutes les mises en
garde concernant lexposition aux radiofréquences et
linterruption de service.
WARNING RF EXPOSURE HAZARD: Ensure the
safety of all personnel. Do not stand in front of the
Invisible Fiber unit (antenna) in order to avoid possible
harmful radio frequency energy exposure. Serious bodily
injury may result.
MISE EN GARDE RF EXPOSURE HAZARD :
Assurer la sécurité de tout le personnel. Ne pas rester
debout devant lunité Invisible Fiber
MD
(lantenne) afin
d’éviter toute exposition dangereuse aux radiofréquences.
Les lésions corporelles serieux sensuivre.