IFU Link Manager
The IFU Link Manager is a local element management software application
that helps you configure and commission the IFU. You use this application to
complete the following procedures:
n IFU configuration
n Antenna alignment
n Link commissioning tests
Power Source
The IFUs require a 48 Vdc power source. The specifications of the power
source are defined in the site engineering folder.
Cabling
IFU installations require two types of cables:
Power
Connects the IFU to the 48 Vdc power source.
Fiber Optic
Connects the IFU to the site equipment cabinet.
Power Cable
The power cable is outdoor/indoor rated. The power cable contains four 12
AWG conductors.
Fiber Optic Cable
For SONET networks, the IFU requires a multimode/single-mode, fiber optic
cable (see Figure 1-1).