Check-Out Procedures
SECTION XII- Check-Out Procedures
Perform the following check-out proce-
dures as outlined and check off items as
completed. When procedures are com-
pleted, the installer should complete the
installation record on page 53.
Check-out Procedures
c Boiler system water chemistry checked and
verified as outlined on page 37.
c The boiler air vent and any automatic air
vents placed within the system are open
one full turn.
c Air is purged from the heating zones and
boiler system piping.
c Burner has been confirmed as properly
configured for Propane application, as out-
lined on page 29 (If applicable).
c Thermostat circuit wiring checked and ver-
ified that no voltage is present to the low
voltage terminals as outlined on page 39.
c Operating Instructions on page 42 were fol-
lowed during start-up.
c Combustion levels and flame pattern veri-
fied as outlined on page 41.
c Measured the rate of input on Natural Gas
as outlined on page 41.
c Checked the incoming gas pressure to the
PRESTIGE to ensure a minimum pressure
of 5”w.c during flow conditions to all gas
appliances and a maximum pressure of
13”w.c during non-flow conditions for
Natural and Propane.
c Adjusted balancing valves and system limit
controls to provide design temperatures to
the primary space heating system.
c In multiple zone applications, adjusted for
correct flow of boiler water to each zone.
c Checked and verified room thermostat(s)
function properly and the thermostat(s)
heat anticipator (if used) was properly set.
c Observed several operating cycles for
proper operation of the PRESTIGE Solo
and the system.
c Set the room thermostat(s) to the desired
room temperature.
c Reviewed all instructions shipped with the
PRESTIGE Solo with the homeowner or
maintenance personnel.
c Completed the Installation Record on page
53.
c Ensure all manuals and other documenta-
tion are returned to the Installation enve-
lope and given to the owner for safekeep-
ing.