Install Instructions (Venting)

20
2.0 Direct Vent Installation of Vent/Air Piping
2.2.4 Direct Vent - Multiple Boiler Installation -
Sidewall
1. On installations of multiple PRESTIGE boilers, ter-
minate each vent and combustion air pipe as
described in this manual.
2. The wall penetration of the vent and combustion air
pipe should be such that the combustion air inlet is
a minimum 12” [30.5 cm] from the adjacent vent pipe
of the other boiler for installations in the U.S as
shown in Fig. 20 on page 21. For installations in
Canada, provide clearances as required by
CAN/CSA B149.1.
The combustion air inlet of the PRESTIGE is defined
as being part of a direct vent system. It is not con-
sidered as a forced air intake. The required clear-
ance of an adjacent boiler vent to a forced air inlet
does not apply in a multiple installation of PRES-
TIGE boilers.
NOTICE
Fig. 11 on page 21 shows one option for vent and
combustion air terminations of multiple PRESTIGE
boilers. Either termination option shown in Fig. 6 or
7 on page 19 can be used for multiple PRESTIGE
boilers. The 12 [30.5 cm] minimum distance
between centerlines of the combustion air and vent
piping must be maintained for any chosen option.
Reference Fig. 6 or 7 on page 19 for the configura-
tion dimensions for the vent and combustion air
inlet terminations for each unit installed in a multi-
ple installation.
NOTICE
NOTICE
Vent Termination
Bird Screen
Horizontal Vent Bird Screen Installation with
Coupling Termination
Fig. 9:
Combustion Air
Termination
Bird Screen
Horizontal Combustion Air Bird Screen
Installation with 90º Elbow Termination
Fig. 10:
Installer must install the factory supplied “bird
screens” on the vent and combustion air termina-
tions.
NOTICE