Trapzilla Solid Separators
AFE
MNL-TSS 15
3.3.5 Two Solids Separators and Two Trapzilla Units
Two Trapzilla Solids Separator and two Trapzilla Grease Interceptors should be installed by placing a
Flow Splitter to divert the water ow to two separate Solids Separators and Trapzilla units in parallel.
Place Two-Way Cleanouts before, between and after the units as shown below, including before and after
the ow splitter. Make sure to connect an outlet vent after the Trapzilla Grease Interceptor. If needed, a
Low Head Flow Control (LHFC) is included with Trapzilla Grease Interceptors (Not included with Solids
Separators) or may be purchased separately and should only be installed after the rst Cleanout and
before the 4” Flow Splitter.
Note: Drawing for reference only. Equipment must be installed in
compliance with all applicable laws, regulations and codes, including
plumbing codes. Installation should be performed by a qualied
1
1
2
2
3
3
4
4
A A
B B
C C
D D
THIS DRAWING CONTAINS PROPRIETARY AND PATENTED MATERIAL. THIS DRAWING MAY NOT BE REPRODUCED IN WHOLE OR PART WITHOUT
WRITTEN CONSENT FROM THERMACO, INC. POSSESSION OF THIS DRAWING DOES NOT CONSTITUTE THE RIGHT TO MANUFACTURE.
POSSESSION OF THIS DRAWING DOES CONSTITUTE AN IMPLIED NONDISCLOSURE AGREEMENT BETWEEN THERMACO, INC. AND THE HOLDER OF
THIS DRAWING. DO NOT DESTROY THIS DRAWING, IT IS THE SO
LE PROPERTY OF THERMACO, INC. AND MUST BE RETURNED UPON REQUEST.
MATERIAL (UNLESS NOTED)
FINISH (UNLESS NOTED)
646 GREENSBORO STREET
PO BOX 2548, ASHEBORO, NC 27203
VOICE 336-629-4651 FAX 336-626-5739
Decimals
.XX +/- .03
.XXX +/- .015
Unless otherwise specified
Dimensions are in inches
Tolerances
Angular
+/- 1
°
CHECKED
SIZE
REV. NO.
DWG NO.
PART NO.
C
SCALE
RELEASE DATE
SHEET OF
ENGINEERING
DRAWN
DATE
THIRD ANG LE PROJECTION
*Use a 4" (100 mm) Two-Way Cleanout for TSS-70,
TSS-95, TZ-400 and TZ-600 Unit Installations
Cleanout*
Cleanout*
Cleanout*
Cleanout*
Cleanout*
Cleanout*
Cleanout*
Outlet
Outlet
Inlet
Trapzilla
TZ-600 unit
Trapzilla
TSS-95 unit
Trapzilla
TZ-600 unit
Trapzilla
TSS-95 unit
Outlet Vent
(Connect to
facility vent)
4" (100mm) Flow Splitter
*Use a Two-Way Cleanout before and after all
Trapzilla Installations
Flow Splitter
The SSOP Support Stand is a one-piece assembly with a conical center that sits
on the oor. It does not add appreciable height to the assembly.
4.0 Above-Ground Installation
4.1 Components for Above-Ground Installations
Using a Support Stand, a Trapzilla Solids Separator may be installed directly on top of the oor in a
location such as a basement or mechanical room.
The SSOP-70/95 should be used with Models TSS-70 and TSS-95.
*This item ships with all -SSA models.
1
1
2
2
3
3
4
4
A A
B B
C C
D D
THIS DRAWING CONTAINS PROPRIETARY AND PATENTED MATERIAL. THIS DRAWING MAY NOT BE REPRODUCED IN WHOLE OR PART WITHOUT
WRITTEN CONSENT FROM THERMACO, INC. POSSESSION OF THIS DRAWING DOES NOT CONSTITUTE THE RIGHT TO MANUFACTURE.
POSSESSION OF THIS DRAWING DOES CONSTITUTE AN IMPLIED NONDISCLOSURE AGREEMENT BETWEEN THERMACO, INC. AND THE HOLDER OF
THIS DRAWING. DO NOT DESTROY THIS DRAWING, IT IS THE SO
LE PROPERTY OF THERMACO, INC. AND MUST BE RETURNED UPON REQUEST.
MATERIAL (UNLESS NOTED)
FINISH (UNLESS NOTED)
646 GREENSBORO STREET
PO BOX 2548, ASHEBORO, NC 27203
VOICE 336-629-4651 FAX 336-626-5739
Decimals
.XX +/- .03
.XXX +/- .015
Unless otherwise specified
Dimensions are in inches
Tolerances
Angular
+/- 1
°
CHECKED
SIZE
REV. NO.
DWG NO.
PART NO.
C
SCALE
RELEASE DATE
SHEET OF
ENGINEERING
DRAWN
DATE
THIRD ANGLE PROJECTION
SSOP-70/95 Support Stand
TSS-95 Trapzilla
Base Model
NOTE: SUPPORT STAND
MUST BE INSTALLED OVER
A CONTINUOUS SURFACE.
NON-CONTINUOUS SUR-
FACES SUCH AS GRATES
ARE NOT SUITABLE FOR
SUPPORT.