Installation and Maintenance Manual

RLC-ADF002-EN 1
Stealth™ RTAE
Installation Completion Check Sheet and Request for Trane Service
Important: A copy of this completed form must be submitted to theTrane service agency that will be responsible for the start-
up of the chiller. Start-up will NOT proceed unless applicable items listed in this form have been satisfactorily
completed.
To: Trane Service Office:
S.O. Number: Serial Numbers:
Job/Project Name:
Address:
The following items are being installed and will be completed by:
Important: Start-up must be performed by Trane or an agent ofTrane specifically authorized to perform start-up ofTrane
®
products. Contractor shall provideTrane (or an agent ofTrane specifically authorized to perform start-up) with
notice of the scheduled start-up at least two weeks prior to the scheduled start-up.
Check boxes if the task is complete or if the answer is “yes.
1. Chiller
Installation meets foundation requirements.
In place and piped.
Isolation pads or elastomeric pads installed (optional).
2. Piping
Water piping flushed before making final connections to the system
Chilled water piping connected to:
Evaporator
Air handling units
Pumps
Flow switch or flow proving device installed (if not factory provided)
Strainer installed and cleaned
Water supply connected to filling system
Systems filled
Pumps run, air bled from system
Strainer installed and cleaned
Relief valve ventilation piping installed (if applicable)
3. Flow balancing valves installed
Leaving chilled water
Leaving condenser water (if applicable)
Optional heat recovery or auxiliary condenser water (if applicable)
4. Gauges, thermometers, and air vents
Installed on both sides of evaporator
5. Wiring
Wire size per submittal and NEC
Full power available
Interconnecting wiring, starter to panel (as required)
External interlocks (flow switch, pumps auxiliary, etc.)
Chilled water pump (connected and tested)
115 Vac power available for service tools
All controls installed and connected
All magnetic starters installed and connected
6. Testing
Dry nitrogen available for pressure testing
Trace gas amounts of R-410A or R-134a available for leak testing, if necessary
7. Refrigerant on job site (if nitrogen charge option, model number digit 15 = 2, is chosen)
8. Systems can be operated under load conditions