Pre-Start
Pre-Start-up Checklist
Before energizing the unit, the following system devices
must be checked:
Is the high voltage power supply correct and in
accordance with the nameplate ratings?
Is the field wiring and circuit protection the correct
size?
Is the low voltage control circuit wiring correct per the
unit wiring diagram?
Is the piping system clean/complete and correct?
Is unit serviceable? (See “Dimensions and Weights,”
p. 13.)
Are all the unit access panels secure and in place?
Is the water flow established and circulating through
all the units?
Is the condensate line properly sized, run, trapped and
pitched?
Does the indoor blower turn freely without rubbing?
Has all work been done in accordance with applicable
local and national codes?
Has heat transfer fluid been added in the proper mix to
prevent freezing if required?