Installation Guide

2023.03.07
1”
5. Spread your mortar base (should be a milk shake consistency), evenly
across the subfloor at the thickness calculated in Step 4.
6. Oset the mortar base 1“ from each outside edge of the pan with
exception of the curb side. Mortar will protrude out from under the curb,
run the finishing trowel along curb face to backfill any excess mortar.
Mark a line on a shim denoting the distance calculated in Step 4. Use the
shim as a depth gauge to verify that the mortar bed
is the depth you need.
7. If there is access from the subfloor below and you followed Step 3a,
then brush primer and PVC adhesive on the inside of the drain and
outside of the cut drain pipe and quickly insert into drain connection, then
be sure the drain pipe extends far enough below the subfloor so it can be
connected to the waste water pipe following the installation.
If there is no access from the subfloor below and you followed step 3b,
then brush primer and PVC adhesive on the drain pipe stubbed up from
the subfloor, then quickly insert the stubbed-up drain pipe properly into
the shower pan drain.**
8. Place the pan in the mud base and firmly but gently shimmy the pan
(applying pressure in drain location first) into the mud so that (i) the drain
is fully supported by mud at the bore hole in the substrate, and (ii) the
ribs are completely filled with the mud alternately applying hand pressure
to the right and left sides of the pan
floor until the pan ribs come within 1/8”
clearance of the subfloor.
9. Using the level, ensure that the pan is level left to right, and front to
back along the splash walls. Also make sure the pan is level left to right
along the curb.
DO NOT USE THE INSIDE OF THE PAN AS AN
INDICATOR SINCE THE PAN IS PREPITCHED.
DO NOT STEP INTO THE SHOWER PAN ONCE
THE SHOWER PAN HAS BEEN SET AND LEVELED
UNTIL THE MORTAR HAS CURED COMPLETELY.
Push to back wall
Lower into
drain
**Pipe adhesion code standards can vary. Please check local plumbing codes.