Installation Instructions

appearance of the control panel if it is correct. Please contact the after-sales
department of Tiancheng Company if any nonconformity is found during various
checks.
3.1.2 Check the internal configuration and connection status of the control panel
Check whether the connections among the components in the control panel are normal.
If it is found that the connecting line falls off, does not conform to the instruction
manual or has unclear identification, please contact the after-sales department of
Tiancheng Company.
3.2 Installation Conditions and Methods of control panel
Dimensions (length × width × height): 360 mm×130 mm×480mm
Temperature:-10℃ ~+55℃.
Relative humidity ≤95%, non-condensing
Installation mode: wall-mounted installation is adopted.
3.3 Power on test
After the control panel enters the site, it should be powered on for startup check.
Check the contents include:
Whether the LCD screen and indicator of the control panel are displayed normally.
Carry out self-test operation, and observe whether the indicator light of the control
panel and each section of the digital tube can be lit, and whether the speaker can emit
three kinds of continuous alarm sounds.
After entering normal monitoring, observe whether there is power fault, whether all
keyboard keys are normal, and check whether the printer with printer is normal.
In case of any abnormality, please inform the after-sales department of Tiancheng
Company.
3.4 External Device check
3.4.1 Device check
Check whether the installation of loop Device meets the design requirements,
eliminate existing faults and make preparations for system connection.
3.5 Wiring and Settings
After the check of the control panel and external device, if all the tests meet the
requirements, please refer to the relevant instructions in Chapter 2 to properly connect
the external device with the control panel and set the multi-loop control panel and
loop manual startup panel.
3.6 Commissioning
3.6.1 System wiring, check circuit and insulation resistance.
3.6.2 Install the detector base.
3.6.3 Register the detectors and modules and install them on the base.
3.6.5 On-site programming-linkage logic programming and Chinese character
annotation input.
3.6.6 Carry out detector alarm test and check whether the annotation content is
consistent with the on-site situation.
3.6.7 Automatic linkage test. If the automatic linkage is abnormal, first manually
check whether the module is normal, if the line and module are normal, check
whether the logical relationship is correct and whether there is any problem with the