1. Ensure the JBOX has been installed with a vertical single gang mud ring. See Figure 15: Vertical Single
Gang Mud Ring and Figure 17-JBOX Vertical Mounting Single Gang Mud Ring, both in Appendix B
beginning on page 35.
2. Turn off power at SS6010 or mounting location using a disconnect switch or breaker lockout/tag out on
appropriate breaker panel.
3. Test that power is off by using a voltmeter.
4. Strip the LINE wire back 0.25 inches.
5. Cap the LINE wire with a wire nut or electrical tape.
6. Cut the COMMON wire so the copper is flush with the insulation.
7. Strip all wires except for COMMON back 0.25 inches.
8. If using an adapter plate, determine which end of the adapter plate should be installed as the top, and
which end should be installed as the bottom:
Figure 2-Adapter Plate
9. Level the high voltage Telkonet JBOX adapter plate and mount to the mud ring with two #6-32 1”