Datasheet
Performance Verification
Equipment Setu
p
Worksheet
This procedure uses a worksheet, as several of the characteristics must be
calculated. The worksheet is located directly after the Test Rec ord.(See Table 2-3
on page 2-6.) As an alternative, there is a spreadsheet version of the Test Record,
available from a link on page 2-2, which will perform these calculations for you.
Procedure
During this procedure you will add and remove 10X attenuators to the signal
path. When more than one attenuator is connected they may be referred to as an
attenuator stack.
1. Connect the equipment as shown. Connect the 50 Ω feedthrough terminator
to the BNC-to-Banana Plug adapter, and attach them to the Multimeter.
2. Power on the instruments for at least 20 minutes.(See page 2-8, Instrument
Warmup Requirements.)
2–10 FCA3000, FCA3100, and MCA3000 Series Specifications and Performance Verification