User guide
APPENDIX “A” 
  THOMSON TECHNOLOGY
©
TYPICAL AUTOMATIC TRANSFER SWITCH 
COMMISSIONING PROCEDURES Model Series TS 870 
iii)  Green “Load” LED is “ON” 
10) To verify all LED’s are operational, perform a “LAMP TEST” operation (lamp test is initiated by 
pressing and holding the 2 push buttons on the TSC 80 faceplate simultaneously “ON” until all 
the LED’s change state). 
11) Prior  to  operating  the  generator,  ensure  it  is  ready  to  be  energized  and  the  site  electrical 
contractor  and/or  owner  (as  required)  give  authorization  to  proceed.    In  preparation  for 
operation, turn the generator’s engine control switch to the “Automatic” start position. 
12) To transfer the generator on load, perform a load test by pressing the Utility Power Fail 
Simulate pushbutton “ON” and holding it for approximately 5 seconds until the LED light above 
the  push  button  changes  state.    The  engine  should  start  following  the  3-second  engine  start 
delay period and the transfer switch will begin transferring to the generator supply once the 2-
second engine warm-up timer expires.  Note: The engine warm-up timer will only begin timing 
once  the  generator’s  output  rises  above  85%  nominal  voltage  and  90%  nominal  frequency. 
Once the Utility power switching device opens, the transfer switch mechanism will pause in the 
neutral  position  for  the  3-second  neutral  delay  period,  then  the  mechanism  will complete  the 
transfer  and  close  the  generator  power  switching  device.    To  determine  correct  operation, 
observe the following on the TSC 80 faceplate: 
i)  Generator Source green LED is “ON” 
ii)  Red LED above mimic bus for the generator source is “ON” 
iii)  Green “Load” LED is “ON” 
iv) Utility Source green LED is “ON” 
v)  Utility Power Fail Simulate yellow LED is “ON” 
vi) Green LED above mimic bus for the Utility source is “OFF” 
13) To terminate the test, press the Utility Power Fail Simulate push button on the TSC 80 faceplate 
again  and  hold  until  the  LED  above  the  pushbutton  changes  state.    The  transfer  switch  will 
begin transferring  to the  utility supply following  the 2-minute  utility return delay period.   Note: 
the utility return delay timer will only begin timing if the utility voltage is above 85% nominal on 
all phases. Once the Generator power switching device opens, the transfer switch mechanism 
will pause in the neutral position for the 3-second neutral delay period, then the mechanism will 
complete the transfer and close the Utility power switching device to return the load to the Utility 
source. Once the load has transferred onto the utility source, the engine will continue to run for 
the 2-minute cool down time delay period and will then it will automatically stop. 
14) Perform  a  power  outage  test  by  opening  the  upstream  utility  feeder  breaker.    The  TSC  80 
controller  Utility  supply  LED  lights  will  de-energize;  the  generator  set  will  start  after  the  3-
second engine start delay has expired.  The generator should transfer on load as described in 
item #12 above. 
15) Return the transfer switch to utility power by re-closing the upstream utility breaker.  The load 
should re-transfer back to the utility supply and the engine should stop as described in item #13 
above. 
16) Repeat tests #12 through 14 two (or more) times to ensure correct operation. 
17) Automatic Plant Exercise Operation (OPTIONAL): If an automatic weekly plant exercise feature 
is  desired,  press  the  GENERATOR  EXERCISE  Mode  push  button  on  the  TSC  80  faceplate. 