2.3 Installation Overview
The next section of this manual covers the physical installation and checkout of the system. When
installing the PLUS hardware, the following steps should be followed to ensure correct system
operation. Use this list as a checklist to make sure that all the necessary configuration steps have
been followed. Each item on the checklist is described in detail below.
a) _______ Unpacking and inspecting hardware
b) _______ Installing and powering the SDP
c) _______ Configuring Reader and solver IP address
d) _______ Ceiling installation of Readers and Antennas
e) _______ Surveying Readers and generating coordinates
f) _______ Connecting the SDP, Ethernet switch, and server
g) _______ Server IP address configuration
h) _______ Server firewall settings
i) _______ PLUS Visualizer software installation
j) _______ Setting data input
k) _______ Checking Reader communications
l) _______ Reader configuration – defining groups and maps
m) _______ Entering floor plan data
n) _______ Calibration Tag placement
o) _______ Calibration Tag configuration
p) _______ Calibrating the system
q) _______ Verifying system performance
2.3.1 Unpacking and Inspecting Hardware
Unpack the PLUS Readers, Antennas, SDP, and Tags, and make sure that no damage has occurred
during shipping. Verify that all mounting hardware and peripheral components are on hand.
2.3.2 Installing and Powering the SDP
Place the SDP in its intended operating location and apply AC power. Also, set up the Ethernet
switch that will service the tracking network at this time. By setting up the SDP first, you can power
up and check the operation of each Reader as it is installed.
Plug each PLUS network cable into a ―SYNC OUT‖ port of the SDP. Be sure that the RJ-45
connector snaps into the receptacle firmly. If the RJ-45 connector will not snap firmly into the
receptacle, do not use this cable, as a reliable connection cannot be guaranteed.
Tip: If you are installing a 24-port SDP, use a 19” equipment rack when possible. You will
be able to connect cables more easily and ensure reliable connections if the SDP is mounted
in a rack.