Installation Guide
PRIOR TO INSTALLATION
• Carefully check flooring material for any defects. Contact your supplier immediately if any defect is found.
• To insure the best color match when installing from two or more cartons, make sure the run numbers on each carton of tile
are the same.
• Allow flooring and adhesive to acclimate to room temperature for 48 hours before, during and after installation. Room
temperature shall be no less than 65º F.
• Remove quarter round, baseboard molding or cove base.
WOOD SUBSTRATES
Suspended wood substrates shall be 1” or thicker, double-construction, strongly constructed, free from spring/deflection and
have minimum of 18” of well-ventilated air space clearance above the ground. A moisture vapor retarder (10 mil or thicker
polyethylene sheeting) should be installed over the ground with overlapped widths and lengths, to reduce moisture vapor
transmission. Top layer of plywood shall be 1/4” minimum thickness underlayment grade plywood. Tarkett recommended
underlayments include the following:
• APA Underlayment Grade Plywood A-C, B-C or C-C Plugged.
• ACCU-PLY
• SurePly
• TECPLY
• ULAY
• C.S.A. (CanPly)
• Proboard
CONCRETE SUBSTRATES
Flooring may be installed over on grade, above grade or below grade concrete subfloors. Concrete floors shall be constructed in
accordance with the American Concrete Institute (ACI) 302.1 Guide for Concrete Floor and Slab Construction. Concrete shall be
finished and cured according to ACI and have a minimum compressive strength of 3500 psi. Floors must be free of any sealers,
curing, hardening or parting compounds that would adversely affect the adhesive. Installation of moisture vapor barrier is
recommended prior to the pouring of on or below grade slabs. Moisture vapor transmission shall not exceed 5 lbs./1000 sq.ft./24
hours per ASTM F-1869 (Anhydrous Calcium Chloride Test). Moisture may also be tested according to ASTM F 2170 (Standard
Test Method for Determining Relative Humidity in Concrete Floor Slabs Using
in situ
Probes). When tested according to this
method, the internal relative humidity shall not exceed 80%. Do not install over gypsum based underlayments.
EXISTING FLOORS
Flooring may be installed over a properly prepared, single layer, non-cushioned existing resilient flooring (residential
applications only). Check flooring for any curled areas around the perimeter or at seams and repair if necessary. Use of a good
quality cementitious based embossing leveler to fill and level any irregularities. Do not install tile over existing tile that is
installed below grade.
WARNING: Do not sand, dry sweep, dry scrape, drill, saw, beadblast or mechanically chip or pulverize existing resilient
flooring, backing, lining felt or asphaltic “cutback” adhesive. These products may contain asbestos fibers or
crystalline silica. Avoid creating dust. Inhalation of such dust is a cancer and respiratory tract hazard. Smoking by
individuals exposed to asbestos fibers greatly increases the risk of serious bodily harm. Unless positively certain that
the product is a non-asbestos containing material, you must presume it contains asbestos. Regulations may require
that the material be tested to determine asbestos content.
TECHNICAL
SERVICE
Vinyl Composition Floor Tile
Installation and Maintenance
Instructions
May 3, 2012