User manual

Table Of Contents
Tandberg Data Operation and Configuration
StorageLoader 1U uses 1U of vertical
rack space. The rails must be installed
in a full U position (The bottom of the
rails must be aligned with the bottom
of a U), see figure 3.2.
Figure 3.2 Rack mount rail
Installing the “Rail Left Assembly”
1. Measure the length between the rear rack mount rails and the front rack
mount rails. If the measurement is shorter than the StorageLoader, move the
two sets of screws M4x12, washers and nuts shown in Figure 3.3.
2. Adjust the “Rail Left Assembly” to fit the measurement in step 1.
3. Use a 7 mm open-end wrench together with the screwdriver to tighten the
two M4x12 screws to fix the rail length.
Note: Using more than two screws will increase the stability of the Rack
Mounting Kit.
4. Place the “Rail Left Assembly” on the left side of the rack, between the rear
rack mount rail and the front rack mount rail.
5. Mount the “Rail Left Assembly” at desired height using one M6x12 screw in
front (upper hole in rail only) and two M6x12 screws at the backside. See
figure 3.4.
Installing the “Rail Right Assembly”
Follow the instruction for left side only using the “Rail Right Assembly” on the
right side of the rack.
14 StorageLoader Installation and User Manual
Use these holes
if rack depth is
equal or longer
than the
StorageLoader
Step 1
Holes to be
used if rack
depth is shorter
than the
StorageLoader
Rear Rack
Mount Rail