Installation Manual
Side of Pole
Add. 02
Installation Recommendations
Auger hole to minimum depth shown in Table 2
6” of hole should be filled with crushed rock or a blocking. This will prevent the pipe from
touching the base of the hole, insuring complete encapsulation of the pipe when concrete is
poured, as well as allowing for water drainage. See Fig. 1
Pipe should be installed vertically no matter the slope of the install site.
Make arrangements to prevent the pipe from twisting prior to pouring concrete.
Pipe should be braced to remain plum until concrete has cured (at least 24 hours).
Figure 1
Side of Pole Foundation Guideline Diagram