Connectionofthecoolingsystemandllingwithcoolantmayonlybecarriedoutbyaqualied
professional.
Connection should be made with copper pipes, which should be cleaned, dried and blown with dry
nitrogen and plugged at both ends.
Whenselectingthecombination,makesuretoproperlymatchthecompressorandtheDXsectionwith
other cooling circuit elements.
When installing, pay attention to the following:
the maximum allowable distance between the DX section and the remaining part of the cooling circuit is 25 m,
discharge pipes should be laid along the shortest route with the minimum practicable number of elbows (elbow
radius R > 3.5 d - pipe diameter).
Check before Commissioning
The implementation of the electrical connections in accordance with the electrical wiring design document,
the condensate discharge line,
the tightness of the soldered joints,
that the pressure testing and drying of the Freon lines has been successfully completed, as well as their connection
totheair-cooledcondenserandllingwithcoolant,
the setup of the cooling system protection elements, such as the high-pressure/low-pressure protection switch,
accordingtothespeciedlevels.Thisalsoappliestothecondensationpressurecontrolswitch.
the correct volume of Freon (no droplets in the inspection glass),
thedryconditionoftheunit(theinspectionglass–colourindicator;dry–wet,inaccordancewiththe
manufacturers instructions),
the correct evaporation and condensation pressure.
Uponcommissioning,makesurethattheelectricheaterinthesumpsufcientlyheatstheFreontoevaporateanyliquid
fractionofFreon(eitherbykeepingtheheateronpermanentlyevenwiththeunitshutdownorbyturningitonin
advance before the unit commissioning).
Medium lling
Priortollingthesystem,extracttheairfromit.Keepdoingthisuntilthepipingsystemisdryandanadequate
vacuumisachieved(see:llingofcoolingsystems).
Thesystemisusuallylledthroughthesuctionconnectiononthecompressor–largercompressorsarettedwith
aspecialconnection.UponreleasingFreonfromthecylinderintothesystem,startthecompressorandkeeplling
untilthespeciedevaporationpressureisreachedandnomorebubblesareseenintheinspectionglass.
1 Splitting module
2 TXV
3 Temperature sensor
4 Capillary TXV
5 Pressure leveling line
6 Humidity indicator
7 mMagnetic valve
8 Drying cartridge
9 Rotolockvalve
10 Collecting chamber