Geniox User Manual Hygienic air handling unit

Table Of Contents
34
| Start-up, adjustments, use, commissioning and unit in out of regular operation for several months
Instructions about configuration of EC motors 7
Printed form for Commissioning protocol - Annex 8
Test report because the unit was delivered with Systemair control system Annex 9
Short description about the main components in the control system —Annex 10
Wiring diagrams about the Systemair control system - Annex 11
K.2 Documentation is available for download
From https://techdoc.systemair.dk
Your local Systemair company is able to provide the below-mentioned documents and data.
Common
This User Manual in an order specific version
Declaration of conformity with production number for this unit and the unique technical data with production number
for this unit
Commissioning Protocol as a Word-file for modification by the installer
Wiring diagrams about the Systemair control system
Components in the air handling unit
Control system for rotary heat exchanger
EC motors
Damper motors
Filter guards
Temperature sensors
Fire thermostats
Smoke detectors
Pressure transmitters
Valves
Valve motors
Humidity sensors
CO2 sensor
Control panel
Humidifier
Manuals about configuration of Systemair control systems— Access
Information about connection of Systemair control systems to Building Management Systems
Other
K.3 Start-up by installer
All protection and safety measures must be met before start-up of the unit. The mains supply voltage must also be
checked too. The mains supply voltage must be measured at the supply terminals in the cabinet.
K.3.1 Checklist, relevant values
K.3.1.1 Checklist prior to start-up
Is the unit assembled correctly with its functions in the correct order? See Annex 2.
Are the sections and ducts assembled correct? See annex i.
Check that fans are not damaged after transportation and installation.
Is the rotary exchanger turning freely?
Are safety guards installed correctly?
If the unit includes integrated heat pump, check whether it is installed and supervised by qualified service personnel.
If the unit contains electric air heater, make sure that the supply isolator disconnects with the unit.
Ducts - are all ducts installed?
output |