Geniox GO User manualv7.2
Table Of Contents
- A Manufacturer
- B Name of machines
- C Declaration of Conformity
- D General descriptions, dangers and warnings
- E The control panel for the control system.
- F Drawings, diagrams, guides and instructions for the use, maintenance and repair
- G Employees in charge of operation/control/maintenance
- H Unintended use and misuse – inappropriate applications for the machine
- I Instructions for unloading and handling on site
- J Installation
- J.1 Installation - mechanical
- J.1.1 Free area in front of and above the unit
- J.1.2 Supporting surface
- J.1.3 Adjustable feet under legs or base frame and transport of sections
- J.1.4 Base frame assembly
- J.1.5 Base frames for outdoor units
- J.1.6 Outdoor units — support under the base frame of the unit
- J.1.7 Installation on the site of unit sections at the base frame when sections are delivered on pallets
- J.1.8 Joining the unit sections
- J.1.9 Fitting the ductwork
- J.1.10 Risk of stack effect by vertical ducts and wind pressure on louvers
- J.1.11 Door alignment
- J.1.12 Lock the doors by using the key
- J.2 Installation - electrical
- J.3 Installation – Pipes for water – hot and chilled, valves and drains
- J.1 Installation - mechanical
- K Installation and assembly instructions for reduction of noise and vibration emissions
- L Start-up, adjustments, use and commissioning
- M Information about the residual risks
- N Instructions on the protective measures during repair and maintenance
- O The essential characteristics of tools which may be fitted to the machinery
- P The conditions of stability during use, transportation, assembly, dismantling when out of service
- Q Instructions for machinery where these are regularly to be transported
- R The operating method to be followed in the event of breakdown. Safe restart.
- S Adjustment and maintenance operations
- T Instructions to enable adjustment and maintenance safely
- U Information on airborne noise emissions exceeding 70 dB(A)
- Annex 1 Technical data – unique data for every unit (in separate cover)
- Annex 2 Assembly of base frame – height 118 mm for unit sizes 10 – 18
- Annex 3 Assembly of base frame – height 118 mm for unit sizes 20 – 27
- Annex 4 Assembly of base frame – height 218 mm for unit sizes 10 – 18
- Annex 5 Assembly of base frame – height 218 mm for unit sizes 20 – 27
- Annex 6 Installation of steel roof in the sizes 10 – 31
- Annex 7 Speed control for rotor and assembly of divided rotor
- Annex 8 Reversible heat pump unit (in separate cover, if heat pump was delivered)
- Annex 9 Menu for internal controller in the heat pump unit (in separate cover, if heat pump was delivered)
- Annex 10 Connection of fan motor and set-up manual for frequency converter
- Annex 11 Commissioning protocol (in separate cover)
- Annex 12 Report with data from final functional test on the Systemair factory
- Annex 13 Short description of main components in the control system
- Annex 14 Wiring diagram (in separate cover)
- Annex 15 Operator’s guide (How to use the Systemair control panel) (in separate cover)
22
| Installation
J.2 Installation - electrical
J.2.1 Installation of cable sealing boxes (only in rotor sections of Geniox GO 27—31)
In rotor sections of Geniox GO 27 —31 installers must
assemble 4 cable sealing boxes. All required parts are
included in accessories.
Part.
No.
Name Notes
1.
Cable connector Connectors are factory preinstalled.
2.
Cable Cables are factory preinstalled. During
installation, cables must be routed through
lower and upper section panels (pos. 6) .
3.
Cable-through
sealing element
Cable-through sealing elements are factory
preinstalled.
4.
Seal holding
plate
Seal holding plates hold cable sealing blocks
(pos. 5) in place. Those plates must be fixed to
the panels using screws (pos. 7).
5.
Cable sealing
block
Foam sealing blocks are used to enclose cables
(pos. 2) and prevent air leakage between
lower and upper sections. To enclose a cable,
first remove a required thickness inner block
tube. Ensure that there is no gap between the
sealant and the cable before fixing it into the
panel.
6.
Bottom panel
of upper
section
Cable sealing blocks must be installed into the
panels (pos. 6 and pos. 7) and fixed with seal
holding plates (pos. 4).
7.
Upper panel of
bottom section
8.
Screws
Screws are used to fix seal holding plates (pos.
4).
J.3 Installation – Pipes for water – hot and chilled, valves and drains
J.3.1 Description
If ordered with the unit, valves and valve motors are packed in a separate box. Water traps are optional. Water traps
are necessary to prevent outside air coming into AHU via drainage.
J.3.2 Pipe connections
Connection pipes on heating- and cooling coils are provided with external thread.
211728 | v7.2