Geniox GO User manualv7.2
Table Of Contents
- A Manufacturer
- B Name of machines
- C Declaration of Conformity
- D General descriptions, dangers and warnings
- E The control panel for the control system.
- F Drawings, diagrams, guides and instructions for the use, maintenance and repair
- G Employees in charge of operation/control/maintenance
- H Unintended use and misuse – inappropriate applications for the machine
- I Instructions for unloading and handling on site
- J Installation
- J.1 Installation - mechanical
- J.1.1 Free area in front of and above the unit
- J.1.2 Supporting surface
- J.1.3 Adjustable feet under legs or base frame and transport of sections
- J.1.4 Base frame assembly
- J.1.5 Base frames for outdoor units
- J.1.6 Outdoor units — support under the base frame of the unit
- J.1.7 Installation on the site of unit sections at the base frame when sections are delivered on pallets
- J.1.8 Joining the unit sections
- J.1.9 Fitting the ductwork
- J.1.10 Risk of stack effect by vertical ducts and wind pressure on louvers
- J.1.11 Door alignment
- J.1.12 Lock the doors by using the key
- J.2 Installation - electrical
- J.3 Installation – Pipes for water – hot and chilled, valves and drains
- J.1 Installation - mechanical
- K Installation and assembly instructions for reduction of noise and vibration emissions
- L Start-up, adjustments, use and commissioning
- M Information about the residual risks
- N Instructions on the protective measures during repair and maintenance
- O The essential characteristics of tools which may be fitted to the machinery
- P The conditions of stability during use, transportation, assembly, dismantling when out of service
- Q Instructions for machinery where these are regularly to be transported
- R The operating method to be followed in the event of breakdown. Safe restart.
- S Adjustment and maintenance operations
- T Instructions to enable adjustment and maintenance safely
- U Information on airborne noise emissions exceeding 70 dB(A)
- Annex 1 Technical data – unique data for every unit (in separate cover)
- Annex 2 Assembly of base frame – height 118 mm for unit sizes 10 – 18
- Annex 3 Assembly of base frame – height 118 mm for unit sizes 20 – 27
- Annex 4 Assembly of base frame – height 218 mm for unit sizes 10 – 18
- Annex 5 Assembly of base frame – height 218 mm for unit sizes 20 – 27
- Annex 6 Installation of steel roof in the sizes 10 – 31
- Annex 7 Speed control for rotor and assembly of divided rotor
- Annex 8 Reversible heat pump unit (in separate cover, if heat pump was delivered)
- Annex 9 Menu for internal controller in the heat pump unit (in separate cover, if heat pump was delivered)
- Annex 10 Connection of fan motor and set-up manual for frequency converter
- Annex 11 Commissioning protocol (in separate cover)
- Annex 12 Report with data from final functional test on the Systemair factory
- Annex 13 Short description of main components in the control system
- Annex 14 Wiring diagram (in separate cover)
- Annex 15 Operator’s guide (How to use the Systemair control panel) (in separate cover)
Installation |
17
Assembly of the base frame is available in this user manual in Annex 2, 3, 4 or5.
There are two types of base frames:
1. 118 mm high base frames
2. 218 mm high base frames
There are 4 different manuals and each of them illustrates the assembly of the 4 different types of base frames:
1. Manual about the 118 mm high base frames for AHUs in the sizes from Geniox GO 10 to Geniox GO 18. The name of
this manual is – Base frame 118 sizes 10 - 18
2. Manual about the 118 mm high base frames for AHUs in the sizes from Geniox GO 20 to Geniox GO 27. The name of
the manual is – Base frame 118 sizes 20 - 27
3. Manual about the 218 mm high base frames for AHUs in the sizes from Geniox GO 10 to Geniox GO 18. The name of
the manual is – Base frame 218 sizes 10 - 18
4. Manual about the 218 mm high base frames for AHUs in the sizes from Geniox GO 20 to Geniox GO 27. The name of
the manual is – Base frame 218 sizes 20 - 27
In Geniox GO sizes 29 to 31 each section has a separate base frame.
Adjustable feet with a distance of maximum 1500 mm between each feet must be fitted under the base frame. The
base frame can be levelled by the adjustable feet.
J.1.5 Base frames for outdoor units
Outdoor units can be installed on both 118 mm and 218 mm high base frames. Hot-dip galvanized base frames are rec-
ommended for outdoor units. Systemair delivers these base frames with the above mentioned adjustable feet.
J.1.6 Outdoor units — support under the base frame of the unit
The installer must provide a frame that supports the base frame of the unit under the inspection side and under the
back side of the unit. The frame must support the base frames of the unit under the entire length of the unit.
Caution
To avoid that the unit may tilt during storm the base frame of the unit must be properly fastened to the
frame provided by the installer
J.1.7 Installation on the site of unit sections at the base frame when sections are
delivered on pallets
1. Lift up the section by hand manual forklifts to the level where the underside of the section is even with the overside
of the base frame.
2. Pull the section to the correct position on the base frame by lifting straps – it is maybe necessary to support the
section by heavy duty furniture trolleys (see the photos below)
Example of heavy duty furniture trolley turned with the wheels
upwards. Placed in this way on the forks of the hand manual
forklifts the heavy duty furniture trolleys are suitable for safe and
careful rolling of the unit sections over to the base frames.
Example of very heavy duty furniture trolleys. Turned with the
wheels upwards and placed on the forks of hand manual
forklifts these heavy duty furniture trolleys are very suitable
for safe and careful rolling of the unit sections over to the base
frames.