2.2.2 HANDLING THE UNITS
During site handling the machine must be left in its original packaging until it has reached the installation position.
The unit must be lifted and transported by means of a forklift truck, pallet truck, winch hoist or through a rope lifting system.
In case of rope lifting, the ropes must be slid underneath the pallet the unit is tted with, and sti spacers must be arranged to ensure
the ropes do not crush the unit's structure during lifting.
To avoid any form of damage it is necessary not to set the machines horizontally during storage, handling and installation
operations.
Handling equipment Position of ropes for lifting
2.2.3 REMOVING THE PACKAGING
If the unit is not to be installed immediately after its arrival on site, it should be stored in its original packaging, in a dry,
enclosed area that is preferably heated during the winter months.
For nal placement of the units the shipping packaging must be removed. Remove the packaging as follows:
1) Cut the protective polyethylene sheet that the unit is wrapped in, paying attention not to damage the paint while cutting.
2) Remove the shock-resistant polystyrene cladding.
Removing the packaging