TM MINI C VRF 8 12KW

135
-
the CHECK button on the outdoor unit s main PCB and complete the cooling mode columns of one Sheet D and
one Sheet E of the system commissioning report for the outdoor unit.
c) Run the system in heating mode with the following settings: temperature 30°C; fan speed high.
d) After one hour, complete Sheet B of the system commissioning report then check the system parameters using
the CHECK button on the outdoor unit s main PCB and complete the heating mode columns of one Sheet D and
one Sheet E of the system commissioning report for the outdoor unit.
6. Finally, complete Sheet C of the system commissioning report.
10.3.2
Once the commissioning test run of each refrigerant system has been satisfactorily completed as per Part 3, 10.3.1
, run the multiple systems that make up a project simultaneously and
check for any abnormalities.