User's Manual

Subfloor EZ Node Hardware Installation Guide
Version 1.0
12
Installing the Subfloor EZ Node
This section provides the steps for installing Subfloor EZ Nodes. After installing the Subfloor EZ
Nodes, see Validating and Commissioning the Subfloor EZ Node Installation to validate the
installation and commission pressure nodes. See Inspecting the Installation to complete the
installation.
In all configurations, hose lengths should not be excessive (short or long) and routing should be
smooth. Avoid hard turns and kinks.
Cabinet to Subfloor
Subfloor EZ Nodes located on the floor
behind the cabinet have a high-pressure
hose/diffuser routed through a hole in
the tile floor and secured to the
stanchion with a cable tie.
Warning: Position the diffusers in areas of still air.
Hose connections may be brittle, particularly in chilled subfloor or cold aisles areas.