User's Manual
Subfloor EZ Node Hardware Installation Guide
Version 1.0
10
General Installation Guidelines
Ensure software installation and required file exports are complete before installing hardware.
Be consistent and neat.
Match all node installations in appearance to ensure optimum data collection
Ensure there are no hard turns or kinks in hoses during routing and installation
Ensure each node provides a representative pressure measurement of the surrounding area
Clean installation surfaces thoroughly with alcohol wipes and allow area to dry
Ensure no tripping or other data center wiring hazards result from Subfloor EZ Node installation
Adhere to safety regulations
Inform customer when relocating nodes to ensure compliance with site safety protocols
Use cable ties and adhesive cable clips as needed.
Attach cable ties such that the locking mechanism is always on the inside
Use diagonal cutters to clip cable tie ends close to its locking mechanism
When external low-pressure hoses are requested, use adhesive cable clips to ensure appropriate
air pressure measurements
Installation Process Flow
Figure 1 shows the installation process flow for installing Subfloor EZ Node.
Figure 1 – Subfloor EZ Node Installation Process Flow