The bypass is constructed with a 45 degree Wye fitting at the bottom of the outlet stack.
The bottom of the Wye is capped and fitted with a tube that connects to the inlet piping or
other drain. The condensation produced in the outlet stack is collected in the Wye fitting
and drained through the bypass tube. The bypass tubing may be insulated to prevent
freezing.
Failure to install a proper condensate collection system voids the
product warranty.
MAINTENANCE
Inspect the product at least once every 12 months for excessive dust and dirt build up on
the impeller (more often in dusty environments). Clean as necessary. The unit must be
disconnected from power during inspection and/or cleaning.
“SYSTEM ON” INDICATOR
Install a “system on” indicator to confirm status. A pressure indicator, manometer, or
vacuum alarm is recommended for this purpose. The Suncourt Air Pressure Indicator is
included with models RDK04 and RDK04-3.
SLAB COVERAGE
The Suncourt Radon Fan provides coverage up to 2000 sq. ft. per slab penetration
depending on type of sub slab material. If one slab penetration does not sufficiently
mitigate the Radon then additional slab penetration points can be added as required.
Detailed Radon information is available on the EPA’s website at:
http://www.epa.gov/radon/