6. Operation
Operation of the Initialisation Device shall be carried out by trained personnel familiar with
the STRYDE system.
During deployment, the Initialisation Device is used to activate the sensor and provide it with
all necessary parameters from the hand-held terminal before planting it in the ground. The
Initialisation Device is flashing blue and green when it is connected to the hand-held terminal
and synchronized to GNSS. The operator shall ensure the terminal is connected to the correct
Initialisation Device and that it is set to Initialize mode. The hand-held device will give an
audio signal to confirm successful initialization. If the Initialisation Device does not have a
flashing blue light, the sensor was successfully initialized with all parameters, but the
synchronization to GNSS has failed. The hand-held device will also indicate this with an on-
screen error message.
The sensors are left in the ground for days to weeks, acquiring seismic data. Upon retrieval,
the operator ensures the Initialisation Device is connected to the hand-held terminal via
Bluetooth and set to Retrieve mode. Then it is used to deactivate the sensor, and at the same
time providing the last synchronisation event. This is acknowledged by the hand-held terminal
using a different audio signal than for deployment.
At the end of each shift, the Initialisation Device is transported back to the hub where it is
cleaned, charged and new parameters are downloaded. Having completed these process
steps, the unit is ready for another day in the field.
Various LED sequences are used to distinguish the Initialisation Device state. In general, all the
states described above can be verified by reading the Initialisation Device Status from an
MPTS.
Initial start-up: Short Blue-Green-Red sequence followed by Long Blue-Green-Red sequence
Active mode: Short green flashes
Low-power mode: Short red flashes
GNSS lock: Short blue flashes
In charger, charging: Red LED on/off
In charger, full: Green LED on
SW download over Bluetooth: Green LED on/off
Loading GNSS almanac data internally: Blue LED on/off, flashing turquoise three times
when completed
The Initialisation Device shall be inspected for damage when returned from the field. Units
with broken housing shall be clearly marked on the top cap so they are easily identified when
placed with other devices. To avoid water ingress in the cleaning process, such damaged units
shall be decommissioned when returned to the hub.
The Initialisation Device shall only be charged in chargers specifically designed for the
STRYDE system. Charging shall be done away from flammable materials, and a fire
extinguisher shall be within reach for emergency use.