Finishing initial commissioning
NOTICE!
After completing basic installation of a master/slave system the devices must then be connected
via the StecaLink bus. Finish the installation of all devices before switching on any devices.
MPPT 6000-M, MPPT 6000-S: If further optional components,
Ä
Chapter 6 ‘Installation and
initial commissioning of optional components’ on page 40, are to be installed and configured,
finish the installation of all devices before switching on the unit.
Basic systems consisting of only one MPPT 6000-M or only one MPPT 6000-S can now be
switched on.
u
Press ESC for 1 s. The basic setting of the status display
appears and initial commissioning is finished.
1. Press SET. The Main menu appears.
2.
Press D, Ñ to select Device On/Off (Fig. left).
3. Press SET. The Device On/Off dialogue appears (Fig. left for
the MPPT 6000-M
display. The MPPT 6000-S display is shown
below).
4.
Press D, Ñ to select On.
5. Press SET. The device switches on.
6. Press ESC for 1 s. The standard status display appears.