5 Initial commissioning of the base system
CAUTION!
Danger of damage to the device and reduction of power. Only technical professionals may
perform the work described in this section.
NOTICE!
A basic system consists of only a single MPPT 6000-M or a single MPPT 6000-S. The description
of the initial commissioning process only covers the absolute minimum settings necessary.
Please consult the relevant sections below for information on further configuration possibilities.
To install and commission a master/slave system the individual units are installed as specified
according to the respective initial commissioning procedure but remain in the OFF
state until all
cabling is completed and all StecaLink bus settings in the master device have been completed.
Topics
1.
Ä
‘Show the basic setting of the status display’ on page 33
2.
Ä
‘Set the language’ on page 34
3.
Ä
‘Set the time’ on page 34
4.
Ä
‘Set the date’ on page 34
5.
Ä
‘Set the battery type’ on page 35
6.
Ä
‘Set the battery capacity’ on page 36
7.
Ä
‘Setting the charge parameters’ on page 36
8.
Ä
‘Switching on the cable compensation’ on page 37
9.
Ä
‘Configuring the temperature sensor’ on page 38
10.
Ä
‘Setting the PV string connection’ on page 38
11.
Ä
‘Finishing initial commissioning’ on page 39
All the measures described in
Ä
‘Installation of the base system’ on page 23 have been taken in
full.
Show the basic setting of the status display
u
If necessary, press ESC for 1 s to show the basic setting of the
status display.