Installation Guide
4 
Rev. 8.2018 
MANDATORY READING 
INSTALLATION UPDATE BULLETIN 
INSTALLATION OF 9KW AND 12 KW STEAM GENERATORS 
When connecting the power supply for the 9kW and 12kW steam generators, there may be some difficulty 
connecting the 8 and 6-gauge wires into the terminal block. In order to make these connections as easy as 
possible, you can remove steam generator wires from the terminal block and wire nut the wires directly to your 
power source. This will make the electrical connections easier. 
USING THE TERMINAL BLOCK 
When using the connection terminal block, the connection can become loose due to expansion and contraction 
from the heat and the small vibrations caused when the unit is running. After the initial installation the 
connection must be checked after 30 days to make sure the connection is still tight (tighten 
if necessary), then the connection should be checked about every 6 months after that. 
If desired, connections may be made directly not using the terminal block. Follow the instructions above for the 
9kW and 12kW steam generators. 
 Terminal block connected Terminal block by-passed using wire nuts 
INSTALLATION OF THE KEYPAD EXTENSION WIRE 
When connecting the keypad and/or the keypad extension wire to the Steam Generator cable, DO NOT TWIST 
THE PLUGS. They are to be PUSHED together, twisting will damage the pins and it is not covered under the 
warranty. 
The escutcheon (temperature detector foundation) for the temperature sensor, comes in a bag inside of 
the keypad box. Also included is the Steam Head. 
Light kits are available for the GS08 Steam Generators. White light and chromotherapy lights are available. 
Contact your place of purchase. 