Installation Guide
17 
Rev. 8.2018 
Blueprint for the control panel 
•  Complete set including: 
•  Control panel 
•  Temperature sensor and holder 
•  User manual 
•  Middle cable between dual panels (6.5 feet) 
Installation instruction of controller 
Important 
Before installing the controller, make sure the steam generator is shut off 
otherwise the controller may not operate properly or be damaged. 
Step One: 
The controller is designed to be installed in the steam room. Points to 
consider: 
1.  4-5 feet from the ground or a convenient height. 
2.  Keep away from the steam nozzle and do not expose under the 
direct spray of steam or water. 
3.  Install on a wall. 
4.  The position of installation should facilitate easy operation and convenient wiring. The controller 
wire is 1.6 feet long, with an extension wire of 20 feet long. The installation of the controller should 
be in a position not more than 21 feet from the steam generator. 
Important 
Do not install the controller under the water pipe or in a position where the keypad is in constant contact with 
water. 
Step Two: 
Drill a round hole of 1 3/8 inches in diameter in a chosen position, no larger or smaller. 
Step Three: 
Pull the controller wire through the round hole, connect it to the extension wire and then to the steam 
generator and connect with the corresponding wire in the generator. Do the same when unplugging.  
Important Do NOT pull tight, fix tight or clip the controller wire in case of damage to it. 
Step Four: 
Start the power supply to the steam generator, check connection, check each item on pages 18-19 to make 
sure all functions work. 
Important 
Before attaching the controller, make sure the steam generator is shut off otherwise the controller may not 
operate properly or become damaged. 