Installation Instructions

19
REVIEW OF APPLICATION
PROCEDURES
1. SUBSTRATE
a. Plywood, OSB or high-density wood fiberboard.
b. Concrete.
c. Insulation boards – all but polystyrene.
2. INSULATION
a. Insulation joints are butted together with no gaps.
b. Correct fastener pattern and quantity used.
c. 100% adhesion of the membrane to the substrate.
3. FIELD SEAMS
a. Seam Primer should be visible past the leading edge of the
field seams (over scrub).
b. There are no wrinkles, void or fishmouths in any portion of
the field seams.
c. All angle changes in the field seams are flashed over with
one ply of Tape Flashing.
d. Seam Tape should extend past leading edge of the seam.
4. FASTENING/TERMINATION BAR
a. Apply Water Stop behind membrane prior to installing the
Fastening/Termination Bar.
b. Install fastener in every hole and maintain a one-fourth inch
(1/4") space between Bars.
c. Fastening/Termination Bar installed on parapet walls a
minimum of twelve inches (12") above the roof deck.
d.
White Caulk applied over top of Fastening/Termination Bar.
5. PENETRATIONS
a. Tape Flashing is applied in two layers a minimum of eight
inches (8") above the roof deck.
b. Pipe Boots have Water Stop applied between the pipe and
boot, are terminated with a Pipe Boot Steel Clamp and are
caulked with White Caulk.
6. METAL EDGE DETAIL
a. Metal Edge is prepped (cleaned and seam primer), and of
sufficient gauge and adequately fastened to withstand wind
uplift.
b. Properly stripped in using six inch (6") wide White Cover
Strip. Cover Strip should extend a minimum of two inches
(2") beyond any fastener.