Installation Instructions
16
2. I
nstall a second layer of twelve inch (12") by twelve inch
(12") Tape Flashing over the rst, but reverse the process by
installing the nine inch (9") half overlapping the previously
installed three inch (3") piece. See Figure 13B. This patch
should extend onto the roof surface a minimum of four inches
(4") and up the vertical a minimum of eight inches (8").
COVER STRIP
Where a protrusion in the roof, such as a pipe or curb opening,
was encountered while installing the RoofKit Rubber Roong
Membrane; the membrane was cut to the nearest edge to allow
easy layout of the membrane. After the eld membrane has
been glued and broomed into place; apply Seam Primer to all
areas to be covered using a scrub pad and allow to dry. After the
Primer has dried, install the Cover Strip over the entire cut in
the eld membrane from the pipe to the end of the membrane,
prior to Pipe Boot installation. See Figure 14.
Rubber
Caulk