Installation Guide

6
If your installation is for a shower only, apply Thread Seal Tape in a clockwise direction to the Tub Outlet Port
and install the included Plug Cap. Wrench tighten. If you are performing a pipe fitting installation, apply Thread
Seal Tape around the pipe threads in a clockwise direction.
7
Referencing the Rough-In Drawing, mount the Valve Assembly to
structure within the wall. Ensuring the Shower Outletand Tub
Outlet are positioned perfectly vertical. Mounting Hardware and
Mounting Structure must be capable of supporting the Valve in use.
Mounting hardware is not included.
If you are performing a
Pipe Fitting Outlet
Installation, please
proceed to Step 8.
OR
If you are performing a
Copper Sweat Outlet
Installation, please
proceed to Step 9.
IMPORTANT:
Install all outlet connections
(Pipe or Copper Sweat)
PRIOR to installing PEX
inlet connections.
9 COPPER SWEAT INSTALLATION
When performing a Copper Sweat installation, it is recommended that you remove the Bonnet with O-Ring ❹, Valve
Cartridge , Integral Stops , and Diverter Cartridge (where applicable) to prevent damage during soldering. Use
a Slip Joint Wrench to unthread and remove the Bonnet . Then remove Valve Cartridge , from Valve Body .
Unthread and remove the Integral Stops using a Socket Wrench equipped with a 9/16” (14mm) Deep Well Socket. If
your Shower Valve is equipped with an Integral Diverter, remove the Diverter Retaining Nut using a Socket Wrench
equipped with a 13/16” (20mm) Deep Well Socket. Remove Diverter Cartridge to prevent damage during soldering.
After soldering (STEP 10) is completed, reinstall the Valve Cartridge , making sure that the mounting posts are aligned
and engaged to the corresponding holes in the Valve Body , with the “H” marking to the left side as shown below.
Verify that the O-Ring is in place on the Bonnet . Install Bonnet over the Valve Cartridge and thread onto the
Valve Body . Tighten securely with Slip Joint Wrench on the machined flats of the Bonnet . Final torque should be
150-168 in*lb. Take care to not over tighten connection or damage may occur. Reinstall the Integral Stops using a
Socket Wrench equipped with a 9/16” (14mm) Deep Well Socket. Final torque should be 70-106 in*lb. If your Shower
Valve is equipped with an Integral Diverter, reinstall the Diverter Cartridge taking care to align mounting posts of
Cartridge with the corresponding holes in the Diverter Valve Body. Install Diverter Retaining Nut and tighten with a
Socket Wrench equipped with a 13/16” (20mm) Deep Well Socket. Final torque should be 35-53 in*lb. Take care to not
over-tighten connections.
NOTE: Never install the valve body upside down!
Socket
Wrench
+
9/16” (14mm)
Deep Well Socke
t
13/16” (20mm)
Deep Well Socke
t
+
Normal Installation
(shown without Bonnet)
H
10 COPPER SWEAT FITTING INSTALLATION
Connect the Shower Outlet Pipe (not included), and Tub Outlet Pipe (not included), by soldering them into
the Valve Vody . Connect the Pipe Elbows (not included), to the end of the shower outlet and tub outlet
pipes. If performing a shower only installation, install Plug Cap in place of tub outlet piping, as shown in
STEP 6. Verify that all connections are soldered. Reassemble Valve components as outlined in STEP 9.
NOTE: The HOT water supply lines go into the H inlet, and the COLD water supply lines
go into the C inlet. Do not use PEX or CPVC between the valve and spout.
SHOWER ONLY
TUB + SHOWER
COLD
HOT