User's Manual Part 1
March 29, 2006 Part ######A revision 00a-DRAFT 41
Chapter 3: Pre-Installation Procedures
Review Site Deliverables List
Table 3.3 shows the paperwork that ships with each base station.
To check the inventory
1 Perform an inventory check using the site deliverables list provided with the E1 package and BOMs.
2 Ensure that all equipment and accessories have been shipped.
3 Document any shortages and report them to the field support coordinator so that any missing equipment
may be procured and delivered to the site as soon as possible.
4 Ensure that the serial number for each piece of equipment is recorded in the base station’s on-site
documentation.
Document Description
Anchor kit Lists installation kit contents
BOM Lists every component in the base station
Shelf inspection checklist Factory inspection of each utility and radio shelf
Table 3.3
Inventory Checklists