Chapter 4: Installation Procedures
9 If all the tests described in steps 58 passed, then the rack is properly grounded
and the main power supply is operating correctly.
If any if the tests failed, investigate and correct the problem. Repeat this procedure
after corrective action is taken. Do not power on the basestation if any of the tests
failed.
10 Disconnect both probes from the power cable.
11 Power off CB 11 on the radio rack by setting it to the OFF (down) position.
12 Reconnect the power cable to the PS0 connector on the utility shelf.
13 Reinstall the three fuses in the PDP in the radio rack by using a 1/4-inch flathead
screwdriver.