Instruction Manual
UM0039_Ai-LB 5k_EN_V01_0223 24
5.3 Cable Connection For Parallel Use
5.3.1 Ground cable connection
Procedure:
Use a screwdriver to fix the ⑧ground wire terminal to the battery ground point refer to Fig. 5.1.1.
5.3.2 Communication cable connection
Multi-Sets in Parallel (LB51100A inside,3 Parallel as an example)
Fig. 5.3.1 Communication cable connection
Procedure:
Connect the communication cable to the corresponding connector refer to Fig. 5.3.3
5.3.3 Power Cable Connection
Procedure:
Connect the power cable to the corresponding connector refer to Fig. 5.1.1
5.4 Set up Master Pack and Slave Pack
Ai-LB 5K is consisted of 1 set of LB51100A . Master Pack and Slave Pack LB51100A can be used as single unit as well
as multi-units (in parallel) mode. The customer must inform supplier if multi-units mode is required. The Master
Pack can be used individually, but Slave Pack cannot be used individually.
Fig. 5.4.1- Dial Diagram Setting